Clearing up misconceptions: The salinity barrier and the Nilwala floods

Clearing up misconceptions: The salinity barrier and the Nilwala floods

05 Jan 2024 | BY Dr. R. Galappatti

The recent experience of high water levels in the lower reaches of the Nilwala Ganga (river) has been attributed by various parties to the construction of the salinity barrier in 2018-2022, 5.4 kilometres (km) upstream of the sea outfall. While it is understandable that the affected communities would blame the most recent construction in the river channel for this, many technically qualified persons have also subscribed to this view without either examining the hydraulic computations or making any measurements at the barrier. We are concerned that ill-considered attempts are being made to interfere with the structural integrity of the barrier and endanger a major piece of water supply infrastructure. 

The salinity barrier is designed to protect the water supply intakes from salinity intrusion and ensure an uninterrupted supply of drinking water to around 600,000 consumers by the year 2035, in the Matara and Hambantota Districts, under the Matara Stage IV Water Supply Project of the National Water Supply and Drainage Board (NWSDB). The conceptual design of the barrier including its dimensions, levels and operating rules was carried out by the Lanka Hydraulic Institute (LHI).  

Regular review meetings were held at the regional level by the NWSDB with participation of the Irrigation Department. The Environmental Impact Assessment (EIA) consultant, the Central Engineering Consultancy Bureau (CECB), also participated, with full access to the details of the ongoing work at all stages of the study. Modifications were made to the study approach and the designs as required. 

The hydraulic studies including design calculations were carried out and the main parameters of the barrier were determined and verified using physical and numerical model studies. This focused on the salinity barrier, particularly its flood impacts, and led to a positive EIA report after public consultations were completed. Detailed designs and the construction of the barrier were carried out by a Korean Company (Kolon-Samsung C&T Joint Venture) with Ceywater Consultants as the local design partner under a design-build contract. 


The salinity barrier

The final design consists of providing a five-bay gated type structure with vertical lifting gates and piers across the inner stream section 5.4 km upstream of the sea mouth, in the river reach between the Thudawa pump station and the Navimana ferry crossing. 

The gates are 10 metres (m) wide and 3.1 m high with the gate sill fixed at minus (-) 2.5 m mean sea level (MSL). The gate top at the closed position is at plus (+) 0.6 m MSL and the gate bottom in the fully open position is to be at 5 m MSL during high and normal flow conditions. This level is above the high flood level, as the top level of the flood bund is only around 4.3 m MSL. Three of the five gates were to be made of two separate sections to allow the upper section to be lowered independently, and to make it possible to lower the upstream pool level when necessary for irrigation water management at the request of the Irrigation Department. 

The sheet-pile cut-off walls were provided across the low-lying areas of the floodplain on either bank to prevent saline water bypassing the main structure during the operation and to ensure that during dry weather, the river flow is confined to the inner channel and not to overflow into the flood plain. In addition to these main features, the gate operating structures, the cut-off walls, access roads, etc. were included in the design.

The barrier is in full conformity to the stipulations in the memorandum of understanding (MoU) signed between the NWSDB and the Irrigation Department in March 2017, and the Irrigation Department granted approval for the NWSDB to implement the project.


Impacts of the salinity barrier

The increase in the river water level during floods, and the operating conditions and concerns of the stakeholders due to the proposed structure were the main considerations in determining the optimal values for the gate openings, the gate sill levels, and other parameters for the design. 

The upstream flooding impact of the barrier design was computed using a numerical model and verified by carrying out a series of physical model tests at the LHI. These were used to verify that the flow pattern around and downstream of the gated structure was satisfactory.

The water levels in the upstream river reach, with and without the barrier, were estimated for different flow conditions including floods up to a 100 years return period. The estimated anticipated water level rise just upstream of the salinity barrier was about one centimetre (cm) maximum during floods of the 100 years return period. There was a higher (4-7 cm) relative water level rise during the bank full and low return period floods. Backwater propagation lengths have been calculated and these anticipated water level rises were considered acceptable. It is relevant to note that the acceptable head loss at the planned Kelani River salinity barrier was fixed in the range of 5-6 cm for a 100 years flood.

As far as the flood impact of the cut-off wall is concerned, the impact will be negligible because this wall, with a top level of only 0.8 m MSL, will be well and truly submerged during a major flood. Further, there is an allegation that debris might trap build-up from the river bed level to the sill level of the gates, and exacerbate flooding. Even if debris is accumulated, its total hydraulic impact is still negligible. Further, a fresh bathymetric survey conducted in December 2023 has even revealed that there is in fact no debris accreted upstream of the gate structure.


Long inundation period 

While it has been demonstrated that the construction of the salinity barrier is not the cause of the recent floods, it is nevertheless necessary to investigate why this long inundation of paddy lands occurred and determine what actions need to be taken to prevent or reduce the probability of a recurrence. 

In this context, it is necessary to examine what happened in May 2017, when there was an extreme flood event in this basin. The flood was caused by an extreme rainfall event of about three days duration that caused a sharp flood peak reaching a daily average water level of 4.32 m MSL at Thalagahagoda on the very next day. The water levels receded to normal levels within the next 10 days while it took seven days to decrease to the flood alert level (1.4 m MSL) at Thalagahagoda. The return period of this flood is said to be between 75 and 100 years.

The duration of the long series of rainfall events that spread out over more than two months from mid-September to end-November 2023, is markedly different, both from the point of view of the basin and the time of year when it took place. While the water level at Thalagahagoda peaked only at 2.92 m MSL in 2023, the level continued to stay above 1.7 m MSL (minor flood level) for almost the entire period (October to mid-November). 

The markedly different nature of this flood, including its extremely slow recession could only be explained by considering the retention (storage) of flood water on the flood plain which is divided into two on either side of the Nilwala flood bund. The area adjacent to the river will drain slowly into the river channel in the normal manner. The water collecting in the “protected area” must be pumped out at a few pumping stations located along the flood bund. The duration of the operation of these pumps is on record, but their pumping rate is not known. An additional point to be considered is that the measured water level profile on the short river reach downstream of the barrier shows a steeper slope indicating a more constricted channel from the railway bridge to the sea.

It is also important to note that the rainfall pattern in 2023 is unusual and unexpected, and that no usual rainfall runoff model could accurately interpret it. The models, in turn, must be more detailed to include the floodplain storage and pumping rates to represent the flood routing performance of the system under such unusual rainfall patterns which might be a trend caused by climate change.

It must also be borne in mind that the Nilwala basin is not a stranger to flooding, though not so late in the year. The steep upper basin that descends suddenly into a largely flat coastal plain is characteristic of all large wet zone rivers in Sri Lanka.


Conclusions

The long duration flooding experience in the Nilwala basin in 2023 has not been caused by the construction of the salinity barrier. A more detailed representation of the flood plains and pump operation is needed to quantify accurately the long recession of the floodplain. 

The marked change in rainfall patterns might be due to a climate change effect and this type of effect might also impact other river basins in the wet zone. This requires attention. The ill-considered removal of the low cut-off wall across the lower floodplain should be restored to avoid the possible shutdown of the water supply intakes in the next dry season.


(The writer is the Chairman of the Lanka Hydraulic Institute)

…………………………………………..