- A response to former CEB GM’s reluctant letter



- Maximise rooftop solar PV: Since rooftop solar does not use transmission infrastructure, scaling the same is the easiest. SLSEA proposes 2 GW solar rooftop systems by 2030 (50% of the total solar capacity needed). Other countries take this path too – in Western Australia, rooftop solar already crosses 50% of total demand during peak generation hours (maximum of 63.7% reached in 2021), and the state is expecting rooftop solar to double by 2030 at which point 100% of demand during peak generation will come from rooftop solar. Australia’s main grid (NEM) expects 77% of the demand to be met by rooftop solar during some hours by 2025.
- Leverage the existing transmission network and reorient the planned routes: We can add generation capacity to the existing network, after doing detailed load flow assessments in the existing transmission network. Many sections of the 220 kV line (for example, the newly built Trincomalee-Veyangoda transmission line) are underutilised and can add capacity. The planned Sampur-Habarana 400 kV line can be moved to Mannar-Anuradhapura at no additional cost, and the proposed 220 kV line from Norochcholai-Veyangoda (planned to support the now cancelled Unit 4) can also be relocated without additional costs to support renewable energy.
- Hybrid generation and twinning: The planned 1000 MW battery storage can be co-located with the planned solar plants to increase yield, shave peak generation during peak and provide power in the evening as well. Floating solar systems on top of hydro reservoirs such that solar electricity is used during daytime with hydro-electricity during the evening (twinning) optimises the existing network. Since the Norochcholai coal plant must be de-loaded during the daytime to support a 70% renewable energy scenario, adding floating solar systems in Puttalam lagoon can leverage the existing transmission network.
- Global best practices with battery storage: It is surprising that CEB’s starting point is building a 400 kV backbone where other countries leverage battery storage to avoid transmission expansions, especially if the maximum load flow is limited to a few hours. Australia is already entertaining virtual transmission lines using battery storage that mimics the line without actually building physical cables. Many countries use community storage to soak up excess energy during daytime and use in the night and avoid transmission upgrades.
